Ideal Checked against MI

Ideal Logic Combi2 (C24, C30, C35)

Combi, natural gas

Combustion figures

FigureNatural gas (G20)
CO₂ at high rate
More infoHide infoTable 1 gives this as CO₂ content at maximum DHW. The air/gas ratio valve is factory set and must not be adjusted.
C24
9.2% ± 0.7
C30
9.3% ± 0.7
C35
9.7% ± 0.7
CO₂ at low rate
More infoHide infoTable 1 gives this as CO₂ content at minimum CH.
C24, C30
8.5% ± 0.7
C35
8.8% ± 0.7
Maximum CO
More infoHide infoAt maximum and minimum rate (commissioning flowchart, MI p. 67).
Less than 350 ppm
CO/CO₂ ratio
More infoHide infoAt maximum and minimum rate (commissioning flowchart, MI p. 67). The servicing schedule (MI 3.1) uses 0.004: above it, go to the cleaning procedure.
Less than 0.0040
O₂
Not given in MI
Working inlet pressure
More infoHide infoMI 1.9: minimum permitted operating pressure delivered to the appliance inlet, allowing 1 mbar loss across the pipework from a minimum meter outlet of 19 mbar. Gas supply is 2H G20 20 mbar (Table 1). The 1:1 gas valve gives full output at inlet pressures as low as 14 mbar. Measured at the inlet pressure test point on the gas service cock, at maximum rate.
Appliance inlet
minimum 18 mbar
Gas rate at maximum
More infoHide infoMaximum DHW input (Table 3). Maximum CH input is 2.512 m³/h on all sizes (Table 2). Calculated at a CV of 38.7 MJ/m³ gross. Check at the meter with no other appliance in use, boiler at full DHW output.
C24
2.512 m³/h
C30
3.135 m³/h
C35
3.657 m³/h
Flue integrity
More infoHide infoAt the air inlet test point, boiler at maximum rate (commissioning flowchart, MI p. 67).
O₂ ≥ 20.6% or CO₂ ≤ 0.2%

From UIN 228296 A05 (August 2022)

Enter service mode for high and low rate

High rate

Steps not added yet. Follow the MI.

Low rate

Steps not added yet. Follow the MI.
Ending the test: follow the MI.

Models and GC numbers

ModelGC numberGas
Logic Combi2 C2447-349-93NG
Logic Combi2 C3047-349-94NG
Logic Combi2 C3547-349-95NG

Source: Ideal Logic Combi2 C24 C30 C35 Installation & Servicing, UIN 228296 A05 (August 2022).

Sections: Table 1 General data; Tables 2 and 3 Performance data; 1.9 Gas supply; 2.24 Commissioning and testing; 2.25 Initial lighting; 2.27 General checks; 2.30 Accessing the installer mode; 3.1 Servicing schedule; Section 6 Flowchart for CO level and combustion ratio check.

Spotted something wrong? Tell us.

Check these figures against the MI for the appliance in front of you, matched by GC number and manual date. Combustion work needs a calibrated analyser and a Gas Safe registered engineer.