Ideal Logic System² (S15, S18, S24, S30)
System boiler, natural gas
Combustion figures
| Figure | Natural gas (G20) |
|---|---|
CO₂ at high rate More infoHide infoTable 1 General Data, CO₂ content at Max. CH. The air/gas ratio valve is factory set and must not be adjusted during commissioning. |
|
CO₂ at low rate More infoHide infoTable 1 General Data, CO₂ content at Min. CH. |
|
Maximum CO More infoHide infoApplies at maximum and minimum rate (Benchmark flowchart). Measured at the flue gas sampling point after readings stabilise. | Less than 350 ppm |
CO/CO₂ ratio More infoHide infoApplies at maximum and minimum rate (Benchmark flowchart). The servicing schedule (section 3.1) gives the same limit as 0.004: above it, carry out the cleaning procedure. | Less than 0.0040 |
O₂ | Not given in MI |
Working inlet pressure More infoHide infoMI section 1.9: allowing 1 mb loss across the pipework from a minimum meter outlet of 19 mb, a minimum of 18 mb will be delivered to the appliance inlet. The boiler can give full output at inlet pressures as low as 14 mb. Table 1 gives the gas supply as 2H - G20 - 20 mbar. Check at the gas cock test point with the boiler at maximum rate. |
|
Gas rate at maximum More infoHide infoTable 2 gas consumption at Max, calculated using a calorific value of 38.7 MJ/m³ gross. |
|
Flue integrity More infoHide infoAt the air inlet (air sample) test point, boiler at maximum rate. The MI says O₂ more than or equal to 20.6% OR CO₂ less than or equal to 0.2%. | O₂ ≥ 20.6% CO₂ ≤ 0.2% |
From UIN 228297 A05 (October 2022)
Enter service mode for high and low rate
High rate
Steps not added yet. Follow the MI.
Low rate
Steps not added yet. Follow the MI.
Ending the test: follow the MI.
Models and GC numbers
| Model | GC number | Gas |
|---|---|---|
| Logic System² S15 (15 kW) | 41-796-85 | NG |
| Logic System² S18 (18 kW) | 41-796-86 | NG |
| Logic System² S24 (24 kW) | 41-796-87 | NG |
| Logic System² S30 (30 kW) | 41-796-88 | NG |
Source: Ideal Logic System² S15 S18 S24 S30 installation & servicing, UIN 228297 A05 (October 2022).
Sections: Table 1 General Data; Table 2 Performance Data; 1.9 Gas supply; 2.24 Commissioning and testing; 2.25 Initial lighting; 3.1 Servicing schedule; Section 6 Flowchart for CO level and combustion ratio check (setting to maximum and minimum rate).
Spotted something wrong? Tell us.
Check these figures against the MI for the appliance in front of you, matched by GC number and manual date. Combustion work needs a calibrated analyser and a Gas Safe registered engineer.